100% isn’t a bad score!
By my reckoning teams from Sydney Light Rail have now completed laying the tracks in Devonshire Street between Chalmers and Randle Streets and South Dowling Street.
The teams are now tidying up and commencing the task of re-laying the road surface and sorting out the kerb and guttering. No doubt spanpoles and overhead will follow.
rewrite this content to 50 words 100% isn’t a bad score!
By my reckoning teams from Sydney Light Rail have now completed laying the tracks in Devonshire Street between Chalmers and Randle Streets and South Dowling Street.
The teams are now tidying up and commencing the task of re-laying the road surface and sorting out the kerb and guttering. No doubt spanpoles and overhead will follow.
Posted by john cowper on 2018-08-08 10:27:57
Tagged: , CSELR , Sydney Light Rail , Surry Hills , Devonshire Street , South Dowling Street , Chalmers Street , Track , Track Laying , Track Slab , tracks , Olivia Gardens , Streetscape , street , Work site , workers , Work team , Transport for NSW , ALTRAC , Infrastructure , Sydney , New South Wales